Fight against landfill strong

Published 10:44 am Monday, February 14, 2011

Developers interested in building a landfill on 5,000 acres in Conecuh County have assured officials through their application for the project that the landfill’s liner will meet or exceed state and federal environmental requirements.

For Ruth Harrell, chairwoman of the Coalition for a Healthier Escambia County, those assurances mean little. She and others opposed to the landfill have studied the effects of the Timberlands Landfill — a smaller facility located just south of where the Conecuh Woods landfill would be built.

“There is documented mercury in the groundwater next to Timberlands Landfill,” Harrell said. “I don’t care if the liner is steel or iron. There is the potential to seep into the groundwater.”

Sign up for our daily email newsletter

Get the latest news sent to your inbox

And Harrell believes Escambia County residents should be just as concerned as Conecuh County residents about the proposal.

The proposed landfill would be located just off Alabama Highway 41, about 6 miles north of the Interstate 65 intersection — about 23 miles north of Brewton.

That proximity should worry Escambia County residents, Harrell said.

“There are potential health effects for the whole region,” she said. “We’re downstream. We’ve already seen this with Timberlands.”

Harrell, who has spent 28 of her 51 years in nursing involved in public health issues, said she is also concerned about the methane gas buildup at the Conecuh Woods site.

“Methane is not destroyed by fire,” she said. “It settles on the ground and the foliage.”

While Conecuh Woods officials have said in their application that they will only accept household waste — that is, municipal solid waste — Harrell pointed out that there is still a possibility for toxic materials to get into household waste if residents don’t dispose of items properly.

“Municipal solid waste is plastic, leather, toxic metals,” she said.

Conecuh Woods officials have said in their application that the lining of the landfill will be a composite system, with 2 feet of natural clay liner topping the soil and a 60-millimeter high density polyethylene geomembrane liner on top of the clay liner.

Officials said a geonet — a triple-layer geosynthetic material — will lay directly over the primary liner, serving as an additional barrier to prent waste material from coming into contact with the primary lining.

The application states that the lining will meet or exceed Alabama Department of Environmental Management and Environmental Protection Agency requirements.

But Harrell said the ADEM data from Timberlands Landfill — which shows that the mercury level in the landfill’s groundwater test wells has exceeded the EPA’s safe drinking water limits — is grounds for worry with another facility that would be located so close.

And although any landfill in the state would have to meet ADEM and EPA rules, Harrell pointed out that “no landfill is a safe landfill.”

“Is the little bit of an economic benefit worth what people will have to pay in public health?” Harrell said. “This is a regional issue; this is a state issue.”

A public hearing on the landfill is set for 9 a.m. Thursday, March 10, at Reid State Technical College in Evergreen.

Initially, the application states, the landfill would be developed on 250 acres, for both offices and the landfill itself. Eventually, the property would have 3,500 acres of buffer zones surrounding a maximum of 1,550 acres of disposal area.

The proposed site is located outside the 100-year flood plain of Escambia Creek, the application states. Initially, the capacity would be 300 to 500 tons per day, increasing to 5,000 tons per day within 10 years, and up to 10,000 tons per day at its peak. The landfill would accept solid waste from states east of the Mississippi River and Louisiana.

If commissioners do not vote on the proposal within 90 days, it would be approved, according to state law.